§ 1066.910 - SHED enclosure specifications.
Enclosures for evaporative and refueling emissions must meet the specifications described in 40 CFR 86.106-96, 86.107-96(a), and 86.107-98(a).
§ 1066.915 - Enclosures; auxiliary systems and equipment.
Enclosures for evaporative and refueling emissions must be equipped with fans, blowers, and measurement and data recording equipment as described in 40 CFR 86.107-98(b) through (h) and (j).
§ 1066.920 - Enclosure calibrations.
Enclosures for evaporative and refueling emissions must meet the calibration specifications described in 40 CFR 86.116-94 and 86.117-96.
§ 1066.925 - Enclosure calculations for evaporative and refueling emissions.
Calculate emissions for evaporative emissions as described in 40 CFR 86.143-96. Calculate emissions for refueling emissions as described in 40 CFR 86.143-96 and 86.156-98.
§ 1066.930 - Equipment for point-source measurement of running losses.
For point-source measurement of running loss emissions, use equipment meeting the specifications in 40 CFR 86.107-96(i).
§ 1066.901 - Applicability and general provisions.
This subpart describes how to measure evaporative and refueling emissions from test vehicles. The provisions of §§ 1066.910 through 1066.930 include general provisions for equipment and calculations related to evaporative and refueling emissions. The provisions of §§ 1066.950 through 1066.985 describe provisions that apply specifically to motor vehicles subject to standards under 40 CFR part 86, subpart S, or 40 CFR part 1037.
§ 1066.950 - Fuel temperature profile.
Develop fuel temperature profiles for running loss testing as described in 40 CFR 86.129-94(d).
§ 1066.955 - Diurnal emission test.
Test vehicles for diurnal emissions as described in 40 CFR 86.133-96.
§ 1066.960 - Running loss test.
Test vehicles for running loss emissions as described in 40 CFR 86.134-96.
§ 1066.970 - Refueling test for liquid fuels.
Except as described in § 1066.975, test vehicles for refueling emissions as described in 40 CFR 86.150-98, 86.151-98, 86.152-98, and 86.154-98. Keep records as described in 40 CFR 86.155-98.
§ 1066.971 - Vehicle and canister preconditioning for the refueling test.
Precondition vehicles for the refueling emission test as described in 40 CFR 86.153-98.
§ 1066.975 - Refueling test for LPG.
For vehicles designed to operate on liquefied petroleum gas, measure refueling emissions as described in 40 CFR 86.157-98.
§ 1066.980 - Fuel dispensing spitback procedure.
Test vehicles for spitback emissions as described in 40 CFR 86.146-96.
§ 1066.985 - Fuel storage system leak test procedure.
(a) Scope. Perform this test as required in the standard-setting part to verify that there are no significant leaks in your fuel storage system.
(b) Measurement principles. Leaks are detected by measuring pressure, temperature, and flow to calculate an equivalent orifice diameter for the system. Use good engineering judgment to develop and implement leak test equipment. You may not tighten fittings or connections in the vehicle's fuel system to prepare the vehicle for testing.
(c) Measurement equipment. Your leak test equipment must meet the following requirements:
(1) Pressure, temperature, and flow sensors must be calibrated with NIST-traceable standards.
(2) Correct flow measurements to standard reference conditions.
(3) Leak test equipment must have the ability to pressurize fuel storage systems to at least 4.1 kPa and have an internal leak rate of less than 0.20 standard liters per minute.
(4) You must be able to attach the test equipment to the vehicle without permanent alteration of the fuel storage or evaporative emission control systems. For any testing that involves pressurizing the fuel system and detecting leaks at access points away from the fuel fill pipe, the gas cap must be installed in the production configuration. For the test point at or near the fuel fill pipe, attaching the test equipment may involve adding an extension to the fuel fill pipe that incorporates the access point to the fuel system. If the extension apparatus has a fixed cap, the vehicle's gas cap must be tested separately as described in paragraph (d)(9) of this section. This separate testing is not required if the extension apparatus incorporates the vehicle's gas cap.
(5) The point of attachment to the fuel storage system must allow pressurization to test system integrity of the fuel tank and of fuel lines and vapor lines reaching up to and including the gas cap and the evaporative canister. The evaporative system test port available on some vehicles is an example of an effective attachment point.
(d) Leak test procedure. Test a vehicle's fuel storage system for leaks as follows:
(1) Refuel vehicle to 40% of its nominal fuel tank capacity.
(2) Soak the vehicle for 6 to 24 hours at a temperature between (20 and 30) °C; record this setpoint temperature and maintain temperatures throughout the leak test at this setpoint temperature within a tolerance ±2 °C.
(3) Before performing the test, purge the fuel storage system of any residual pressure, bringing the system into equilibrium with ambient pressure.
(4) Seal the evaporative canister's vent to atmosphere and ensure that the vehicle's purge valve is closed.
(5) Attach the leak test equipment to the vehicle.
(6) Pressurize the fuel storage system with N
(7) Maintain gas flow through the system for at least 180 seconds, ensuring that the flow reading is stable for an effective leak diameter of ±0.002 inches.
(8) Use the following equation, or a different equation you develop based on good engineering judgment, to calculate the effective leak diameter, d
(9) Repeat the test described in this paragraph (d) for each access point described in the application for certification. Use each test result (without averaging) to determine whether the vehicle passes the leak standard.
(10) Gas caps may need to be tested separately for leaks as described in paragraph (c)(4) of this section. Test the gas caps using commercially available flow equipment such as that used for inspection-and-maintenance programs for motor vehicles to determine a leak rate in cubic centimeters per minute resulting from a sustained tank pressure of 7.5 kPa. Correct the leak rate to standard reference conditions, based on the measured leak rate corresponding to atmospheric pressure. The corrected leak value may not exceed 60 cubic centimeters per minute.
(11) You may use special or alternative test procedures as described in 40 CFR 1065.10(c).
(e) Equipment calibration. Use good engineering judgment to calibrate the leak check device.