(a) A grantee may submit to the Department a request for approval—
(1) To use not less than 65 percent of the grant funds to pay the wages and benefits described in § 641.864(a);
(2) To use the percentage of grant funds specified in § 641.867 to pay for administrative costs as described in § 641.856;
(3) To use the 10 percent of grant funds that would otherwise be devoted to wages and benefits under § 641.873 to provide participant training (as described in § 641.540(e)) and participant supportive services to enable participants to successfully participate in a SCSEP project (as described in § 641.545), in which case the grantee must provide (from the funds described in this paragraph) the wages for those individual participants who are receiving training from the funds described in this paragraph, but may not use the funds described in this paragraph to pay for any administrative costs; and
(4) To use the remaining grant funds to provide participant training, job placement assistance, participant supportive services, and outreach, recruitment and selection, intake, orientation and assessment.
(b) In submitting the request the grantee must include in the request—
(1) A description of the activities for which the grantee will spend the grant funds described in paragraphs (a)(3) and (a)(4) of this section;
(2) An explanation documenting how the provision of such activities will improve the effectiveness of the project, including an explanation of whether any displacement of eligible individuals or elimination of positions for such individuals will occur, information on the number of such individuals to be displaced and of such positions to be eliminated, and an explanation of how the activities will improve employment outcomes for the individuals served, based on the assessment conducted under § 641.535(a)(2); and
(3) A proposed budget and work plan for the activities, including a detailed description of how the funds will be spent on the activities described in paragraphs (a)(3) and (a)(4) of this section.
(c)(1) If a grantee wishes to amend an existing grant agreement to use additional funds for training and supportive service costs, the grantee must submit such a request not later than 90 days before the proposed date of implementation contained in the request. Not later than 30 days before the proposed date of implementation, the Department will approve, approve as modified, or reject the request, on the basis of the information included in the request.
(2) If a grantee submits a request to use additional funds for training and supportive service costs in the grant application, the request will be accepted and processed as a part of the grant review process.
(d) Grantees may apply this provision to individual sub-recipients but need not provide this opportunity to all their sub-recipients.