§ 250.1753 - After I decommission a pipeline, what information must I submit?

Within 30 days after you decommission a pipeline, you must submit a written report to the Regional Supervisor that includes the following:

(a) A summary of the decommissioning operation including the date it was completed;

(b) A description of any mitigation measures you took; and

(c) A statement signed by your authorized representative that certifies that the pipeline was decommissioned according to the approved application.