§ 98.480 - Definition of the source category.
(a) This source category pertains to carbon dioxide (CO
(1) You are using the standard designated as CSA/ANSI ISO 27916:19, (incorporated by reference, see § 98.7) as a method of quantifying geologic sequestration of CO
(2) ou are not reporting under subpart RR of this part.
(b) This source category does not include wells permitted as Class VI under the Underground Injection Control program.
(c) If you are subject to only this subpart, you are not required to report emissions under subpart C of this part or any other subpart listed in § 98.2(a)(1) or (2).
§ 98.481 - Reporting threshold.
(a) You must report under this subpart if your CO
(b) The requirements of § 98.2(i) do not apply to this subpart. Once a CO
(1) Discontinuation of reporting under this subpart must follow the requirements set forth under Clause 10 of CSA/ANSI ISO 27916:19 (incorporated by reference, see § 98.7).
(2) CO
(i) Cessation of CO
(ii) Cessation of hydrocarbon production from the project reservoir; and
(iii) Wells are plugged and abandoned unless otherwise required by the appropriate regulatory authority.
(3) You must notify the Administrator of your intent to cease reporting and provide a copy of the CO
(c) If you previously met the source category definition for subpart UU of this part for your CO
§ 98.482 - GHGs to report.
You must report the following from Clause 8 of CSA/ANSI ISO 27916:19 (incorporated by reference, see § 98.7):
(a) The mass of CO
(b) The mass of CO
(c) The mass of native CO
(d) The mass of CO
(e) The mass of CO
(f) The mass of CO
§ 98.483 - Calculating CO2 geologic sequestration.
You must calculate CO
(a) You must calculate the mass of CO
(b) The manner by which associated storage is quantified must assure completeness and preclude double counting. The annual mass of CO
(c) You must quantify the total mass of CO
(1) You must include the total mass of CO
(2) The CO
(i) The native CO
(ii) CO
(3) The sum of the quantities of allocated CO
(d) You must calculate the total mass of CO
§ 98.484 - Monitoring and QA/QC requirements.
You must use the applicable monitoring and quality assurance requirements set forth in Clause 6.2 of CSA/ANSI ISO 27916:19 (incorporated by reference, see § 98.7).
§ 98.485 - Procedures for estimating missing data.
Whenever the value of a parameter is unavailable or the quality assurance procedures set forth in § 98.484 cannot be followed, you must follow the procedures set forth in Clause 9.2 of CSA/ANSI ISO 27916:19 (incorporated by reference, see § 98.7).
§ 98.486 - Data reporting requirements.
In addition to the information required by § 98.3(c), the annual report shall contain the following information, as applicable:
(a) The annual quantity of associated storage in metric tons of CO
(b) The density of CO
(c) The annual quantity of CO
(1) The annual total mass of CO
(2) The annual mass of native CO
(d) The annual mass of CO
(e) The annual total mass of CO
(1) Loss of CO
(2) Loss of CO
(3) Loss of CO
(4) Loss of CO
(f) The total mass of CO
(g) Annual documentation that contains the following components as described in Clause 4.4 of CSA/ANSI ISO 27916:19 (incorporated by reference, see § 98.7):
(1) The formulas used to quantify the annual mass of associated storage, including the mass of CO
(2) The methods used to estimate missing data and the amounts estimated as described in Clause 9.2 of CSA/ANSI ISO 27916:19 (incorporated by reference, see § 98.7).
(3) The approach and method for quantification utilized by the operator, including accuracy, precision, and uncertainties (see Clause 8 and Annex B of CSA/ANSI ISO 27916:19 (incorporated by reference, see § 98.7)).
(4) A statement describing the nature of validation or verification including the date of review, process, findings, and responsible person or entity.
(5) Source of each CO
(6) A description of the procedures used to detect and characterize the total CO
(7) If only the mass of anthropogenic CO
(8) Any documentation provided by a qualified independent engineer or geologist, who certifies that the documentation provided, including the mass balance calculations as well as information regarding monitoring and containment assurance, is accurate and complete.
(h) Any changes made within the reporting year to containment assurance and monitoring approaches and procedures in the EOR operations management plan.
§ 98.487 - Records that must be retained.
You must follow the record retention requirements specified by § 98.3(g). In addition to the records required by § 98.3(g), you must comply with the record retention requirements in Clause 9.1 of CSA/ANSI ISO 27916:19 (incorporated by reference, see § 98.7).
§ 98.488 - EOR Operations Management Plan.
(a) You must prepare and update, as necessary, a general EOR operations management plan that provides a description of the EOR complex and engineered system (see Clause 4.3(a) of CSA/ANSI ISO 27916:19 (incorporated by reference, see § 98.7)), establishes that the EOR complex is adequate to provide safe, long-term containment of CO
(1) Geologic characterization of the EOR complex.
(2) A description of the facilities within the CO
(3) A description of all wells and other engineered features in the CO
(4) The operations history of the project reservoir.
(5) The information set forth in Clauses 5 and 6 of CSA/ANSI ISO 27916:19 (incorporated by reference, see § 98.7).
(b) You must prepare initial documentation at the beginning of the quantification period, and include the following as described in the EOR operations management plan:
(1) A description of the EOR complex and engineered systems (see Clause 5 of CSA/ANSI ISO 27916:19 (incorporated by reference, see § 98.7)).
(2) The initial containment assurance (see Clause 6.1.2 of CSA/ANSI ISO 27916:19 (incorporated by reference, see § 98.7)).
(3) The monitoring program (see Clause 6.2 of CSA/ANSI ISO 27916:19 (incorporated by reference, see § 98.7)).
(4) The quantification method to be used (see Clause 8 and Annex B of CSA/ANSI ISO 27916:19 (incorporated by reference, see § 98.7)).
(5) The total mass of previously injected CO
(c) The EOR operation management plan in paragraph (a) of this section and initial documentation in paragraph (b) of this section must be submitted to the Administrator with the annual report covering the first reporting year that the facility reports under this subpart. In addition, any documentation provided by a qualified independent engineer or geologist, who certifies that the documentation provided is accurate and complete, must also be provided to the Administrator.
(d) If the EOR operations management plan is updated, the updated EOR management plan must be submitted to the Administrator with the annual report covering the first reporting year for which the updated EOR operation management plan is applicable.
§ 98.489 - Definitions.
Except as provided in paragraphs (a) and (b) of this section, all terms used in this subpart have the same meaning given in the Clean Air Act and subpart A of this part.
Additional terms and definitions are provided in Clause 3 of CSA/ANSI ISO 27916:19 (incorporated by reference, see § 98.7).