U.S. Code of Federal Regulations
Regulations most recently checked for updates: Aug 29, 2025
Subject to the notice requirements of §§ 157.205(b) and 157.208(c), the certificate holder is authorized to acquire, construct, modify, replace, and operate natural gas facilities that are used to transport either a mix of synthetic and natural gas or exclusively revaporized liquefied natural gas and that are not “related jurisdictional natural gas facilities” as defined in § 153.2(e) of this chapter. The cost of a project may not exceed the cost limitation provided in column 2 of table 1 to § 157.208(d). The certificate holder must not segment projects in order to meet this cost limitation.