U.S. Code of Federal Regulations
Regulations most recently checked for updates: Aug 28, 2025
Pre-award Costs. EPA award recipients may incur allowable project costs 90 calendar days before the Federal awarding agency makes the Federal award. Expenses more than 90 calendar days pre-award require prior approval of EPA. All costs incurred before EPA makes the award are at the recipient's risk. EPA is under no obligation to reimburse such costs if for any reason the recipient does not receive a Federal award or if the Federal award is less than anticipated and inadequate to cover such costs.