Insert the clause at 552.236-15, Schedules for Construction Contracts, in solicitations and contracts if construction, dismantling, demolition, or removal of improvements is contemplated. Use the clause:
(a) With its Alternate I when the contract amount is expected to exceed the simplified acquisition threshold and a design-bid-build project delivery method will be followed.
(b) With its Alternate II when the contract amount is expected to exceed the simplified acquisition threshold and a design-build project delivery method will be followed.
(c) With its Alternate III when the contract amount is expected to exceed the simplified acquisition threshold and a construction-manager-as-constructor project delivery method will be followed.