As prescribed in 970.3200-11, insert the following clause:
(a) The Contracting Officer may reduce or suspend further advance, partial, or progress payments to the Contractor upon a written determination by the Senior Procurement Executive that substantial evidence exists that the Contractor's request for advance, partial, or progress payment is based on fraud.
(b) The Contractor shall be afforded a reasonable opportunity to respond in writing.