United States Code
USC most recently checked for updates: Jun 09, 2025
Nothing in subsections (b)(1), (b)(2), and (b)(3) of this section shall affect any existing or future methodology employed by a Transmission Organization for allocating or auctioning transmission rights if such Transmission Organization was authorized by the Commission to allocate or auction financial transmission rights on its system as of
The Commission may exercise authority under this chapter to make transmission rights not used to meet an obligation covered by subsection (b) available to other entities in a manner determined by the Commission to be just, reasonable, and not unduly discriminatory or preferential.
Nothing in this chapter relieves a load-serving entity from any obligation under State or local law to build transmission or distribution facilities adequate to meet the service obligations of the load-serving entity.
Nothing in this section shall provide a basis for abrogating any contract or service agreement for firm transmission service or rights in effect as of
The Commission shall ensure that any entity described in section 824(f) of this title that owns transmission facilities used predominately to support its own water pumping facilities shall have, with respect to the facilities, protections for transmission service comparable to those provided to load-serving entities pursuant to this section.
This section shall not apply within the area referred to in section 824k(k)(2)(A) of this title.
This section does not authorize the Commission to take any action not otherwise within the jurisdiction of the Commission.
An entity that to the extent required to meet its service obligations exercises rights described in subsection (b) shall not be considered by such action as engaging in undue discrimination or preference under this chapter.