As provided in this section, the Commission may issue and amend licenses, as appropriate, for closed-loop pumped storage projects.
Not later than 180 days after
In establishing the expedited process under this section, the Commission shall convene an interagency task force, with appropriate Federal and State agencies and Indian tribes represented, to coordinate the regulatory processes associated with the authorizations required to construct and operate closed-loop pumped storage projects.
The Commission shall seek to ensure that the expedited process under this section will result in final decision on an application for a license by not later than 2 years after receipt of a completed application for such license.
Before issuing any license for a closed-loop pumped storage project, the Commission shall assess the safety of existing dams and other structures related to the project (including possible consequences associated with failure of such structures).
In issuing or amending a license for a closed-loop pumped storage project pursuant to the expedited process established under this section, the Commission may grant an exception from any other requirement of this subchapter with respect to any part of the closed-loop pumped storage project (not including any dam or other impoundment).
In granting an exception under paragraph (1), the Commission shall consult with the United States Fish and Wildlife Service, the National Marine Fisheries Service, and the State agency exercising administration over the fish and wildlife resources of the State in which the closed-loop pumped storage project is or will be located, in the manner provided by the Fish and Wildlife Coordination Act (16 U.S.C. 661 et seq.).
The Commission, in addition to the requirements of section 803(e) of this title, shall establish fees which shall be paid by an applicant for a license for a closed-loop pumped storage project that is required to meet terms and conditions set by fish and wildlife agencies under paragraph (3). Such fees shall be adequate to reimburse the fish and wildlife agencies referred to in paragraph (3) for any reasonable costs incurred in connection with any studies or other reviews carried out by such agencies for purposes of compliance with this section. The fees shall, subject to annual appropriations Acts, be transferred to such agencies by the Commission for use solely for purposes of carrying out such studies and shall remain available until expended.
Not later than 6 months after
Not later than 1 year after
The Commission shall establish criteria that a pumped storage project shall meet in order to qualify as a closed-loop pumped storage project eligible for the expedited process established under this section.
Nothing in this section affects any authority of the Commission to license a closed-loop pumped storage project under this subchapter.